The scenario is:
Main contract between Employer and principal Contractor = Delay Damages defined at £795.00 per day.
Subcontract between principal Contractor and Subcontractor = Delay Damaged also defined at £795.00 per day.
Am I correct in saying that in this scenario the delay damages in the subcontract have been defined. Therefore should the instance occur where the Employer makes a claim against the Contractor for delay damages due to a fault by the subcontractor, the Contractor can only claim a maximum of £795.00 per day from the subcontractor and does not have the ability to also claim for his own loss and expense in addition to this?