JCT D&B 2011 - Is it possible for a subcontractor to claim additional supervision costs under a variation claim bought about by a contractor accelerating the works

0 votes
86 views
asked Dec 14, 2016 in JCT Contracts by JoSmith (120 points)  
   

1 Answer

0 votes
The simple answer is almost certainly yes. When pricing the VO you need to take into account the circumstances in which the VO arises and how that may differ from rates used in pricing the original works. Acceleration is such a circumstances in the same way that working in a confined space or more onerous conditions would be.
answered Apr 5 by Rob Horne (8,690 points)