NEC3 ECC: Transfer of non used TRA to other floats

0 votes
88 views
So, is this correct to say, in a nutshell,  that;

- Unused TRA on activities on the critical path is to be transferred to terminal float.
- Unused TRA on activities not on the critical path is to be transferred to total float.
asked Dec 11, 2016 in NEC3 Time by anonymous  
   

1 Answer

+1 vote
Yes in a nutshell that is correct!
answered Dec 11, 2016 by Glenn Hide (29,340 points)