Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,044 questions

4,190 answers

430 comments

33,575 users

Register its Free

Download here

NEC3 ECC: Transfer of non used TRA to other floats

0 votes
72 views
So, is this correct to say, in a nutshell,  that;

- Unused TRA on activities on the critical path is to be transferred to terminal float.
- Unused TRA on activities not on the critical path is to be transferred to total float.
asked Dec 11, 2016 in NEC3 Time by anonymous  
   

1 Answer

+1 vote
Yes in a nutshell that is correct!
answered Dec 11, 2016 by Glenn Hide (26,200 points)