Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,143 questions

4,307 answers

482 comments

33,960 users

Register its Free

Download here

NEC3 ECC: Negative Risk in a Negative Compensation Event?

0 votes
192 views
We are assessing a de-scope of works which gives rise to a neagtive compensation event. With additional works - as the client did not like the figures the risk register was showing - we have agreed a percentage uplift for risk.
Should this also be applied to negative CE's?
asked Oct 3, 2016 in NEC3 Compensation Events by anonymous  
   

1 Answer

0 votes
Not quite sure what you mean by "With additional works - as the client did not like the figures the risk register was showing - we have agreed a percentage uplift for risk". However, ignoring that, it can be confirmed that the same way a compensation event should be built up for a "positive" one should be applied to a "negative" one. That means it should include risk, and also any time savings if planned Completion is coming forward, and the saving should also include fee as well, but Completion Date would not come forward.
I do get that a Contractor is not going to go "all out" in maximizing risk within a quote that is going to reduce the Total of the Prices, but the rules are meant to be the same. This is the one type of quote that the Contractor is trying to make as low as possible, and for once the Project Manager is trying to increase!
answered Oct 3, 2016 by Glenn Hide (27,780 points)