Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is a free web based knowledge capture and sharing service, a help desk and library of 1000+ high-quality questions and answers, delivered and curated by a panel of industry experts.

3,970 questions

4,110 answers

417 comments

33,459 users

Register its Free

Download here

NEC3 ECC: Under option C, if a quotation for a proposed instruction under clause 61.2 is not accepted because the proposed instruction is not now required, can the Contractor submit an NCE for the preparation costs of the quote, if so which is the correct clause under 60.1.

0 votes
asked Sep 16, 2016 in NEC3 Compensation Events by Claud Blackwood  
   

1 Answer

0 votes
No!

There is no where in the contract that allows for this recovery (unfortunately). However, too many of these will mean you spend less time on them and they include more risk, so not in an Employers interest to load you with lots of unlikely events.
answered Sep 16, 2016 by Glenn Hide (24,730 points)