Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,283 questions

4,472 answers

579 comments

34,694 users

Register its Free

Download here

NEC3 ECS: TRA for removed scope

+1 vote
131 views
My Subcontractor has TRA aginst testing activities. We are removing the testing from the Subcontract. I know TRA can't be used by the Contractor, but can this TRA be removed as the scope is removed, or does this TRA get reallocated to other activities in the programme?
asked Jul 22, 2016 in NEC3 Time by Stephenwilliams82 (620 points)  
   

1 Answer

+1 vote
The TRA does not get "reallocated". However, if a critical path item has been deleted then this will bring forward planned Completion so it is "converted" into terminal float which the Subcontractor in this instance still owns. Non-critical activities the deletion of activities and the  TRA will be converted to "total float" which the Parties share.
answered Jul 22, 2016 by Glenn Hide (32,620 points)