Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,143 questions

4,307 answers

482 comments

33,960 users

Register its Free

Download here

NEC3 ECC: Can the PM exclude the retention of Suppliers in the Contractor's IPA?

+1 vote
131 views
Can the PM exclude the retention of Suppliers (not classified as Subcontractor in clause 11.2 (17) in the Contractor's IPA?
in clause 11.2 (23)  "Defined Cost is - the amount of payments due to Subcontractors for work which is subcontracted WITHOUT taking account of amounts deducted for - retention"
PM's opinion this is applicable only to Subcontractor (clause 11.2 (17)). But for the Suppliers with retention provision on their Supply agreement, retention can be excluded in the contractors IPA. This is consistent in Clause 50.2 - The amount due is
•    the Price of Work Done to Date.
Clause 11.2 (29) The Price for Work Done to Date is the total Defined Cost which the Project Manager forecasts will have been PAID by the Contractor up to the end of a period three weeks after the next assessment date plus the Fee.
Thus, the PM argue that since the retention will not be Paid until completion of the contract, Contractors IPA  should only include amount payable (cash out) up to next assessment plus fee.
asked Jul 18, 2016 in NEC3 Payment by acc (480 points)  
recategorized Jul 18, 2016 by acc
   

2 Answers

+1 vote
Based on the clauses you have referred to the answer is Yes, the PM can exclude retention until it is due to be paid out. But I would suggest some further checks before this can be confirmed as the correct decision:

1. Check if the suppliers are Subcontractors under the contract- refer to clause 11.2(17)
2. If they are not Subcontractors then clause 11.2(23) confirms that the Defined Cost is determined using the Schedule of Cost Components, so check what is included under the relevant category.

I hope this helps, but if you need further advice, please don't hesitate to get in touch.
answered Jul 25, 2016 by Dave Parkinson (1,660 points)  
+1 vote
Yes, I think the PM is within his rights to exclude the Supplies retention if they are not due to be paid before the next assessment date.

In your question you refer to 11.2(29) stipulating "........ up to the end of a period three weeks after the next assessment date plus the Fee." This is not the standard definition, so must have been amended by a Z clause. The standard definition is " .......... will have been paid by the Contractor before the next assessment date plus the Fee,"
answered Jul 25, 2016 by dave bates (4,570 points)