Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is a free web based knowledge capture and sharing service, a help desk and library of 1000+ high-quality questions and answers, delivered and curated by a panel of industry experts.

3,970 questions

4,110 answers

417 comments

33,459 users

Register its Free

Download here

NEC3 ECC: Reduction in lump sum cost on an Option A contract

+2 votes
An item of plant/equipment that was included in the lump sum price is now not required.
Can the employer ask for a reduction in the lump sum price in the form of a negative compensation event?
asked Jul 15, 2016 in NEC3 General by anonymous  
   

1 Answer

+1 vote
If this is a change to the Works Information that you are talking about here (not clear if you mean "Plant and Materials" or "Equipment" - check their definitions for the subtlety) then yes this would be a compensation event. That would then be assessed using defined cost (not activity schedule rates unless you both agree) plus fee to generate the saving.

Easy test would be if they want more of this thing would that qualify as a compensation event? If so then the same would apply if they are removing elements that was stated in Works Information.   

If however this was temporary works, such as a crane is not now needed to install something then that would not be a compensation event and the total of the Prices would remain as is. If this is permanent works identified in the Works Information that is no longer required then this would result in a compensation event.
answered Jul 15, 2016 by Glenn Hide (24,730 points)  
Worth noting also that the cost element may be reduced by the time element cant be. Completion dates cannot be brought forward due to negative compensation events.