Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,283 questions

4,472 answers

579 comments

34,694 users

Register its Free

Download here

NEC3 ECC: Issuing Certificates

+1 vote
753 views
Clause 30 states that the Project Manager certifies completion.

Similarly, clause 43 states that the Supervisor issues the Defects certificate.

However, neither clause says who the certificate are issued to.  Are they issued to the Contractor and copied to the Employer or vice versa?
asked May 27, 2016 in NEC3 Time by Brian (480 points)  
   

2 Answers

+2 votes
I believe that the answer is in clause 13.6 which states

The Project Manager issues his certificates to the Employer and the Contractor. The Supervisor issues his certificates to the Project Manager and the Contractor.
answered May 30, 2016 by dave bates (5,130 points)  
+1 vote
I wrote this out - Clause 13.6 states "The Project Manager issues his certificates to the Employer and the Contractor. The Supervisor issues his certificates to the Project Manager and the Contractor." - then spotted Dave's answer waiting for approval below.
answered May 30, 2016 by Jon Broome (24,610 points)