Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

3,979 questions

4,116 answers

420 comments

33,482 users

Register its Free

Download here

NEC3 ECC: What happens if the Employer has terminated the contract but does not instruct the Contractor to leave the Site, under P2?

+1 vote
295 views
When should the Contractor leave? What payment will be due to the Contractor if he remains on site?
asked May 24, 2016 in NEC3 Termination by anonymous  
   

1 Answer

+2 votes
Let's presume that the PM has issued a termination certificate under clause 90.1, which means that the Contractor then does no further work under clause 90.5. So even without the instruction under P2 the Contractor should do no further work, and if he does then this is at his own risk as he may not get paid for it as he'd be in breach of contract for doing so.

You should note that P2 deliberately refers to the Site and not Working Areas, therefore if for example the Contractor's site establishment and materials storage areas are outside the Site but within Working Areas the Employer's authority does not extend to these areas.

From an Employer's point of view, you may have another contractor lined up to complete the works, in which case you would want to ensure the Contractor had left the Site so as not to disrupt the incoming contractor.

P2 contains three elements which the Employer may instruct:

(1) leave the Site
(2) remove any Equipment, Plant and Materials and
(3) assign the benefit of any subcontract

This gives the Employer the flexibility (use of the word 'may' means he can choose to do it or choose not to do it) to respond to the termination in the way that best suits his plans.

By not instructing the Contractor to leave the Site, the Employer is allowing the Contractor to leave when it suits him to do so, which may not fit with the Employer's plans.
answered Jun 16, 2016 by Neil Earnshaw (3,420 points)