Thanks Glen. Should the the example you gave in this article, re contractor founding an obstruction on pipe route, be a notified CE rather than an EW as ‘risk’ has occured: the obstruction is there!
1 Like
Broadly yes, although from memory in the example it was not known straight away it would be a problem, hence the initial early warning. Very soon after it was known to be an issue so was then notified as a CE.