Under NEC3 PSC Option E we have submitted a completed package order including CD Pt2 to the client including our fee proposal which sets out a budget cost to complete each activity required under the contract.
Where we go beyond the number of hours for each activity and hence over the budget, is this remeasurable or would a compensation event be required to recover the cost for exceeding the amount of hours previously stated?
Perhaps it could be an employers risk if included in the CD?