Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,092 questions

4,244 answers

451 comments

33,766 users

Register its Free

Download here

NEC3 ECC: Updating the acceted programme to point of CE

+1 vote
165 views
An accepted programme exists in Jan 2015. The next programme for acceptance is submitted in March 2015 with progress, additional change etc included but is rejected.
An NCE is issued in April 2015. Can the progressed but rejected programme be used as a basis for accessing the impact of the CE?
asked Aug 25, 2015 in NEC3 Time by Julian  
   

1 Answer

+2 votes
Julian - The time assessment must be carried out such that you are assessing the impact that the compensation event has on planned Completion. That, however, has to be modelled on an Accepted Programme. So, no you shouldn't use the rejected March programme as the baseline but the Accepted Programme current at the time of the event, here the one in January. Updating for progress (so that you remove delay being caused other than by the compensation event) should then be carried out and you may well draw on the March data to do that.
answered Aug 26, 2015 by Rob Horne (8,850 points)