Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

3,979 questions

4,116 answers

420 comments

33,482 users

Register its Free

Download here

JCT DB11 contract - Contractor liability for Employer controlled Subcontractor

+1 vote
846 views
how is extension of time handled under a design and build contract (db11), if the Subcontractor (employed by the Employer) makes error in setting out works, is the main Contractor entitled to extension of time, or would the Employer be entitled to claim LAD's?

The contract is db11 design and build, what is the process for extension of time, if the main contractor needs more time as a result of a named specialist subcontractor (appointed by the employer) makes an error. What would be the situation if the subcontractor was employed by the main Contractor??
asked Apr 19, 2015 in General by anonymous  
   

1 Answer

+1 vote
Generally the Employer is responsible for the accuracy of site information and ground conditions unless the JCT 2011 DB contract has been amended to provide otherwise.

Extensions of time (adjustments to the completion date) are permitted only where a relevant event listed under 2.26 occurs and the works are likely to be delayed beyond completion (2.25). The process is under clause 2.24-2.25. The contractor can give notice of the material circumstances (2.24) or the Contract Administrator can grant an extension based on the information available (2.25.5).

If the default, whether an act or omission, was by an Employer Person (ie a contractor or consultant appointed directly, as you state) then 2.26.6 might apply; the facts might also come under a Change (5.1). If it was by a subcontractor (as normally defined ie employed by the contractor) then it would not. More information would be needed to provide a definitive response.

If the contractor is not granted an extension and the CA has acted reasonably, then the Employer may be able to deduct LADs provided overall completion of the project is delayed and the Employer issues a notice of non-completion under clause 2.28.
answered Apr 20, 2015 by Sarah.Fox (280 points)